212th Ave SE Non-Motorized Improvements: SE 24th St to Crossings at Pine Lake

Subscribe to project updates.

 

Summary

This project creates new sidewalk and landscape planter strip on the west side of 212th Ave SE between SE 24th and the Crossings at Pine Lake subdivision. Also, both sides of the street will receive widened shoulders to accommodate bicyclists.

Project Updates

Construction is underway and scheduled to be substantially complete at the end of August. Final planting will wait for cooler weather in autumn.

Goals and Benefits

The project extends sidewalk from The Crossings at Pine Lake subdivision south to SE 24th Street where it will connect with existing soft pedestrian paths. Additionally, the narrow shoulders will be widened to accommodate bicycles.

Timeline

Construction began July 17, 2017.

Substantial Completion: August 23, 2017 (tentative)

Final Planting: September 25 - October 6, 2017 (weather dependent)

Budget

$827,130

Public Involvement

See the "Comment" hotlink at left, or "Subscribe" hotlink above the summary.

Permits, Environmental Review

January 19, 2016 - JARPA application submitted to U.S. Army Corps of Engineers

February 12, 2016 - SEPA application submitted to Sammamish Community Development